"Electric Networks of Armenia" Company informs its subscribers that as a result of a fire in the 6 kV closed distribution equipment of the "Vardashen" 110/35/6 kV Substation, the 23 cells of the 6 kV feeder, as well as the operational current and voltage equipment providing their relay protection, were completely out of order and became useless.
For more than 36 hours, the professional units of the National Electric Power Company have been carrying out intensive and urgent work aimed at restoring the electricity supply to the areas without power due to the fire that broke out in the substation.
The attached pictures show the works of disassembly and removal of the burned equipment, as well as the transportation and installation of the new equipment (newest generation), inspection of the feeding cables and their final adjustment.